Oncology Hospital in Mosul
Oncology Hospital in Mosul
Client: UNDP
Contract Value: 16,946,644 USD
Completion date: The Project is On-going
Description: Removing the old damaged building, Construction of The New three floors Hospital with 100 Beds with about 17,000 m2 including all Buildings and Services.
1- Clean and remove of Debris for the old building.
2- Construct of Eight ( male & female) wards with total of 122 beds including all utilities and services.
3- Construct of Laboratories, Administration Dept. & Conference hall.
4- Supply and Erect ( 6 ) Passengers and Service Elevators.
5- Supply and erect Complete Electricity system with Four Generators with total of 5 MVA and Fuel tanks & pumps.
6- Supply and erect Four Transformers 11/0.4 KV ( 1250 KVA ).
7- Supply and erect Pager & Call System, Fire Detection System ,CCTV ,Central Time.
8- Construct Fire Fighting detection and Firefighting system including Tanks, Pumps, Pipes & Fittings.
9- Supply and erect Complete Oxygen , Medical Gas & Vacuum Units.
10- Supply and Install Three Chillers & Three cooling towers with total cooling capacity of ( 1500 Tr ), ( 14 ) AHU’s , Split A/C units , Air Fans & ( 11000 m ) insulated Ducts.
11- Supply and Install Three Hot water boilers ( 770 Kw ) for each.
12- Supply and install all Electrical Wiring inside and outside buildings with about ( 6000 ) Electrical points.
13- Supply and erect the High Voltage ,Low Voltage , Signal Wires and Control network including the overhead and ground cables ( more than ten Kilometers ).
14- Supply and install Dozens of Electrical panels ( H.V. & L. V. ) including Distribution Panels , Operating panels ..etc
15- Supply and Install different types of pumps ( 25 pumps ).
16- Supply and erect UPS Systems ( 120 KVA ) with all Batteries & panels.
17- Supply and Coating X-ray rooms with Lead sheets ( 7400 m2 ).
18- Construct of Special underground Tank to collect the polluted wastes.
19- Prepare and furnish the Gardens with total area of ( 2000 m2 ).